Commission Works for Jeneponto 2x125MW CFSPP Project

01 / 02 / 2012 - Project Date

Commission Works for Jeneponto 2x125MW CFSPP Project The first utilization of the 150 kV GIS was during the power back feeding on early of Febuary. After hte Power Back-feeding, then the process of commissioning was to enter. on Febuary, the Unit #1 had its Boiler Hydrostatic Test. Continuing the process of commissioning, the process then was continued with Boiler Chemical Cleaning of Unit #1. 2weeks after the process successfully performed, the First Firing of Unit #1 was performed. Still in the same day with the First Firing, the Steam Blowing of Unit #1 was performed.