01 / 06 / 2008 - Project Date
PLTU Cilacap 2x300MW unit #1 Overhaul D&C complete PLTU Cilacap unit #1 overhaul with the cooperation of our parent company - ZTPC from April to June 2008. During this overhaul, D&C also induced new technology - Tini-oil Ignition System into unit #1 of PLTU Cilacap and complete some technical alteration successfully. The owner of PLTU Cilacap appreciated D&C for our effort and spirit during the overhaul period.