09 / 02 / 2011 - Project Date
Overhaul Condition Commisioned by S2P in February 2011, D&C company carried out grade C+ for Unit #1 April 19 2011 the unit started up on April 20 at 05.58 generator synchronized The main defects of unit #1 were eliminated totally through the minor overhaul. According to the regulations of the unit operation at 05.58 April 20 2011 Generator synchronized to the power grid for commercial operation after finished all test items The grade C+ overhaul took 18days, 2hours and 43minutes from unit #1 parallel off to parallel to power grid Conclusion Overhaul of grade C+ has been accomplished at 11.00 April 21 2011 and inspected and accepted by s2p FAC conclusion Until on April 19 2012 at 10.00 am already expire 1years warranty period, now unit #1 operation well owners formally granted fac