01 / 05 / 2012 - Project Date
Synchronization of PLTU Jeneponto After all of the equipments and sub-systems commissioning were completed, the Unit #1 had its first synchronization on may 2012. The electric power was firstly delivered entering the electrical grid of Makassar System in that day. All of the construction works of Unit #2 and also the commissioning process of Unit #1 were still continously ongoing since then. The remaining commissioning process of Unit #1 were the 168 hour reliability run, Load Rejection Tests, and Performance Test; they were all continued by PT. D&C Engineering Company with highly-spirited motivation in order to fulfill best achievements. On August 2012, the Unit #1 had its Certificate of Feasible Operation, issued by PT. PLN (Persero) Jasa Sertifikasi. And then, October 2012, the Certificate of Feasible Operation were issued by PT. PLN (Persero) Jasa Sertifikasi for both units of PLTU Jeneponto.