April 14th 2023, Sumbagsel-1, South Sumatera. The first pouring concrete of the foundation for boiler at PLTU Sumbagsel-1 commenced at 9.00 AM.

After Bore Pile construction finish, continue by preparation works consist of topographical survey, staking out and joint survey, main access road from Batching Plant to Boiler Area, next is the sequence of work for Boiler Foundation consist of lean concrete, install rebar & formwork for foundation, install rebar for short column, pre-pouring concrete for Boiler foundation. After having an inspection to guarantee all according to specification and got the approval from all parties, the pouring concrete work commenced.

The dimension of foundation is 16m x 12m x 2m using concrete K-300 and the quantity of concrete is approximately 384 m³ and carried out 1 time pouring.