18 / 09 / 2021 - Press Release
D&C complete PLTU Cilacap 2x300 MW unit #1 Overhaul with the well cooperation of D&C Team from from 26 August-17 September 2021. During this Overhaul, all found faults and damages has been eliminated. The equipments and functions of mechanical, electric and i&c had been recovered and can be used very well. The owner of PLTU Cilacap appreciated D&C's effort which finally lead the overhaul successfully.
Dismantling cross pipe of steam turbine |
Dismantling RSV (Reheat Steam Valve) |
Dismantling cross pipe of steam turbine |