PLTU JENEPONTO 2X135 MW FIRST INSPECTION, UNIT 3A and 3B OVERHAUL

04 / 09 / 2021 - Press Release

PLTU JENEPONTO 2X135 MW  FIRST INSPECTION, UNIT 3A and 3B OVERHOUL

First inspection for PLTU Jeneponto 2X135 MW, 3A and 3B was start. First, 3B start shutdown at 23:00 June 27th 2021 and synchronized to the grid at 09:30 June 16th, 2021. Next was unit 3A, start shutdown at 00:00 o’clock, July 18th , 2021 and synchronized to the grid on 19:00 August 4th , 2021. The overhaul was successfully finished based on schedule. Completed to eliminate all damage and some modification. Both of unit already normal operation and can reach the maximum load on last NDC test.

Thanks to all the hard works, excelent coordination and performance from D&C team to get this amazing achievements!